At a glance: Selecting a plan for the American Indian Cultural Center and Museum in Oklahoma City

At a glance: Selecting a plan for the American Indian Cultural Center and Museum in Oklahoma City
Published: October 17, 2012
Advertisement

At a glance

Selecting a plan

These six plans were presented to the board overseeing construction of the museum Aug. 26, 2004. The board selected the Vision Plan, despite having acquired less than a quarter of the project costs.

1. Minimal Plan: $53.5 million

2. Minimal Plan, alternate No. 1: $63.4 million

3. Minimal Plan, alternate No. 2: $69.6 million

4. Preferred Plan: $85.3 million

5. Preferred Plan, alternate No. 1: $91.9 million

6. Vision Plan: $136.1 million

Source: 2012 audit of the Native American Cultural

and Education Authority


Trending Now


AROUND THE WEB

  1. 1
    Twelve Weeks To A Six-Figure Job
  2. 2
    New York Pain Clinic Doctor Is Sentenced in Overdose Deaths of 2 Patients
  3. 3
    Time Lapse: Amsterdam Light Festival
  4. 4
    Baby Jesus gets GPS
  5. 5
    NORAD's Santa Tracker Began With A Typo And A Good Sport
+ show more