Kemper costs rise $40 million on start-up reserve

Published on NewsOK Modified: January 28, 2014 at 6:41 pm •  Published: January 28, 2014
Advertisement
;

JACKSON, Miss. (AP) — The Southern Co. says it may cost another $40 million to finish the $5 billion-plus power plant and mine it's building in eastern Mississippi's Kemper County.

The Atlanta-based parent of Mississippi Power Co. said Tuesday that it would set aside money in the plant's budget to cover possible start-up problems. Critics have warned the technology, which turns soft lignite coal into a gas, extracts chemicals and burns the gas to generate electricity, may not work as designed. A coal gasification plant built by Duke Energy in Edwardsport, Ind., using different technology, struggled during its startup phase.

Mississippi Power said it, and not its 186,000 customers from Meridian to the Gulf Coast, will pay the additional money.

"We're just having to highlight that we see an additional risk on startup," spokeswoman Christy Ihrig said Tuesday. She said that the company analyzes future costs and decided now was the time to set the budget for startup contingencies.

Mississippi Power has already tested the plant's gas-powered turbines, which are similar to those used in a conventional natural gas plant. It's supposed to start the gasifier by June and start producing gas from its chemical-stripping unit by September. The company says the Kemper plant, which it calls Plant Ratcliffe, will enter commercial operation before year's end.

It's the fourth straight quarter that Southern has bumped up Kemper's cost the day before it announced its earnings to investors. The utility has now written off $1.18 billion in cost overruns, and is also forgoing $133 million in federal tax credits because of delays in the plant's completion. The plant complex was originally supposed to cost $2.8 billion.