Xcel blamed for cost overruns at Monticello plant

Published on NewsOK Modified: July 9, 2014 at 9:37 am •  Published: July 9, 2014
Advertisement

MINNEAPOLIS (AP) — An investigation by Minnesota utility regulators blames Xcel Energy Inc. for major cost overruns during a project to upgrade its nuclear plant in Monticello.

Xcel disagrees that it's to blame.

The Star Tribune reports (http://strib.mn/1oHbOmI ) that experts hired by Minnesota utility regulators found Xcel managers didn't fully plan for the job and didn't have adequate oversight. The investigation also found Xcel misleadingly blamed the U.S. Nuclear Regulatory Commission for some costly delays.

The project rose from an estimated $320 million in 2008 to $665 million when it was completed last year. The final cost could reach $748 million.

The utility is asking regulators to have ratepayers pay for the cost of the upgrade.

Xcel will file a reply to issues raised in the investigation next month.


AROUND THE WEB

  1. 1
    Landry Jones hoping to take advantage of increased opportunity with Steelers
  2. 2
    Oklahoma security guard high on pot when he shot man, say attorneys
  3. 3
    OHP: Vehicle crashes into crane near U.S. 81 and I-40
  4. 4
    Jaguars GM doubts Justin Blackmon will ever play again
  5. 5
    The glamorous life of a frequent traveler is a lie, researchers say
+ show more

FEATURED JOBS



× Trending energy Article